Last update on 30.01.2021 15:13
Find out contracts, concession companies and funding sources
Database of concession projects and Public Private Partnerships signed by the Albanian government during the period 2004-2020.
The concession contract was concluded between the Ministry of Economy, Trade and Energy and the companies Edil Europe srl and Rinia 04 shpk.The object of the contract is: financing, design, construction, commissioning, administration, maintenance of hydropower plants Myhejani 1, 2, 3 in the course of the Tropoja brook, Tropoja district. At the end of the concession period, the facilities will be transferred to the Contracting Authority.
Alps Energy - 100% of the sharesIn the Founding Act, the partners of the company are Rinia 04 shpk (41% of the capital) and EdilEurope (59% of the capital).