Albania's Public Private Partnerships

Find out contracts, concession companies and funding sources

Database of concession projects and Public Private Partnerships signed by the Albanian government during the period 2004-2020.

Construction of hydropower plants Sheba 1, 2, 3, 4

The concession contract was concluded between the Ministry of Economy, Trade and Energy and the companies Arilta - B shpk and Aurora Konstruksion shpk.
The object of the contract is: financing, design, construction, commissioning, administration, maintenance of hydropower plants on the river Zalli i Tarit, Mirdita district. At the end of the concession period, the facilities will be transferred to the Contracting Authority.

Company
Zalli i Tarit
Company Description
Object: to implement the concession contract. The company was established on 03.03.2011. Its capital is 100'000 ALL.
Shareholders

Aurora Konstruksion- 50% of the shares
Arilta B, New Generation- 50% of the shares

Related Persons and Entities
Agron Jaupllari - current administrator (16.03.2016 - 16.03.2021)
Ilir Tafaj - administrator (03.03.2011 - 16.03.2016)
On 31.03.2011, the company Zalli i Tarit shpk has temporarily suspended its activity. Status was "Active" and becomes "Suspended". On 08.08.2014 the company has reactivated the activity.

Location