Construction of hydropower plants in the Malind water basin

The concession contract was concluded between the Ministry of Energy and Industry and the company Kotorri - SL shpk.
The object of the contract is: financing, design, construction, commissioning, administration, maintenance of hydropower plants HEC no. 1, 2, 3 in the Malind brook. At the end of the concession period, the facilities will be transferred to the Contracting Authority.

Company
Kotorri - SL
Company Description
Object of activity: activity in the field of construction, design and investment in construction. Retail hydrocarbon trade. Carriage service and parking. Coffee bar. The company was established on 10.07.2008. Its capital is 51'200'000 ALL.
Shareholders

Shyqyr Kotorri - 30% of the shares
Merit Kotorri - 70% of the shares
In the Founding Act, the partner of 100% of the capital was Hikmet Kotorri.

Related Persons and Entities
Merita Kotorri - current administrator (05.08.2013 - 13.07.2021)
Shyqyri Kotorri - former administrator (10.07.2008 - 05.08.2013)