Construction of hydropower plants on the Zheja Stream

The concession contract was concluded between the Ministry of Economy, Trade and Energy and the companies Piroli shpk and Demal shpk.
The object of the contract is: financing, design, construction, commissioning, administration, maintenance of hydropower plants Zheja 1 and Zheja 2 in the catchment area of the stream Zheja, Lezha. At the end of the concession period, the facilities will be transferred to the Contracting Authority.

Company
Clas - As Energy
Company Description
Objective: generation, transmission and distribution of electricity, construction of hydropower plants and rehabilitation of existing hydropower plants. Forest works. Import - export of minerals, explosives, etc. The company was established on 31.10.2014. Its capital is 100'000 ALL.
Shareholders

Xhevahir Perlesi - 50% of the shares
Geg Piroli - 50% of the shares

Related Persons and Entities
Geg Piroli - current administrator (31.10.2014 - 31.10.2019)

Location