Construction of Lengarica 1 and Lengarica 2 hydropower plants

The concession contract was concluded between the Ministry of Economy, Trade and Energy and the company Hasi Energji shpk.
The object of the contract is: financing, design, construction, commissioning, administration, maintenance of hydropower plants Lengarica 1 and Lengarica 2, Petran commune, Përmet district. At the end of the concession period, the facilities will be transferred to the Contracting Authority.

Company
Lengarica & Energy
Company Description
The company was established on 25.06.2008, with a share capital of 856'000'000 ALL. The company was created specifically to implement the concession contract. Its head office is at the address: Municipal Unit no. 2, Street "Jul Variboba", Villa no. 10, Tirana.
Shareholders

Hasi Energji - 50% of the shares.
Enso Hydro Energy - 50% of the shares.
In the Founding Act, Hasi Energji owned 100% of the shares.

Related Persons and Entities
Jurgen Gaisberger - current administrator (17.05.2019 - 17.05.2022)
Ylli Halili - current administrator (14.11.2017 - 14.11.2020)
Aida Nani - former administrator (13.11.2014 - 14.11.2017)
Fatbardh Çangu - former administrator (17.12.2012 - 13.11.2014)
Georg Schweighofer - former administrator (17.12.2012 - 21.03.2019)
Wolfgang Kröpfl - former administrator (24.02.2010 - 17.12.2012)
Elton Beqi - former administrator (20.04.2011 - 17.12.2012)
Enri Leka - former administrator (25.06.2008 - 20.04.2011)

Location