Last update on 30.01.2021 15:13
Find out contracts, concession companies and funding sources
Database of concession projects and Public Private Partnerships signed by the Albanian government during the period 2004-2020.
The concession contract was concluded between the Ministry of Economy, Trade and Energy and the companies Anglican Energy Limited, Montagues LLP and Alba Ndërtim shpk.In addition to the Suha 1 hydropower plant, a concession has been granted for the construction of the Sula 2 hydropower plant on the same river. The operating regime of the 2 hydropower plants depends on each other. The concessionaire must cooperate with the concessionaire of the Suha 2 hydropower plant.The object of the contract is: financing, design, construction, commissioning, administration, maintenance of Suha 1 hydropower plants in the Suha stream, Gjirokastra district. At the end of the concession period, the facilities will be transferred to the Contracting Authority.
Anglican Energy Limited - 100% of the sharesIn the Founding Act the partners of the company are Montagues LLP (40% of the shares), Anglican Energy Limited (35% of the shares) and Alba Ndërtim shpk (25% of the shares).