Last update on 30.01.2021 15:13
Find out contracts, concession companies and funding sources
Database of concession projects and Public Private Partnerships signed by the Albanian government during the period 2004-2020.
The concession contract was concluded between the Ministry of Economy, Trade and Energy and the companies Gramozi Ndërtim Projektin shpk and Ujanik 2 shpk.The object of the contract is: financing, design, construction, commissioning, administration, maintenance of Ujanik 2 hydropower plant in the course of Ujanik streams, Skrapar district. At the end of the concession period, the facilities will be transferred to the Contracting Authority.
Ujaniku 2 - 100% of the sharesAccording to the Founding Act, the company was established by Gramozi Ndërtim Projektim shpk and Ujaniku 2 shpk.