Construction of Zerec 1 and Zerec 2 hydropower plants

The concession contract was concluded between the Ministry of Economy, Trade and Energy and Korça Ndërtim Prodihim - A shpk and Flonja shpk.
The object of the contract is: financing, design, construction, commissioning, administration, maintenance of hydropower plants Zerec 1 and Zerec 1 in the course of the catchment area of the Dushari stream, Korça district. At the end of the concession period, the facilities will be transferred to the Contracting Authority.

Company
EnRel Hydro shpk
Company Description
The company was established on 11.03.2013, with a share capital of 100'000 ALL. The company was created to implement the concession project.
Shareholders

HY - Life - 50% of the shares
Korça Construction Production - A - 50% of the shares
In the Founding Act, Aurel Naumi owns 100% of the shares.

Related Persons and Entities
Aurel Naumi - current administrator (11.03.2013 - 11.03.2023)

Location