Albania's Public Private Partnerships

Find out contracts, concession companies and funding sources

Database of concession projects and Public Private Partnerships signed by the Albanian government during the period 2004-2020.

Construction of hydropower plants Dobjot i Madh, Arrëz, Miras, Menkulas, Bracen and Kuc

The concession contract was concluded between the Ministry of Economy, Trade and Energy and Arela shpk, Konstruksion shpk and 2T shpk.
The object of the contract is: financing, design, construction, commissioning, administration, maintenance of hydropower plants Dobjot i Madh, Arrëz, Miras, Menkulas, Bracen and Kuç along the river Devoll, Devoll district. At the end of the concession period, the facilities will be transferred to the Contracting Authority. The contract is in the form of BOT (construction, operation and transfer of ownership and operation at the end of the concession contract to the Contracting Authority).

Company
D6 shpk
Company Description
Temporary merger of the companies Arela shpk, Konstruksion 93 and 2T shpk. The company was established on 17.08.2010, with a share capital of 100'000 ALL. Its head office is at the address: Reshit Petrela Street, Palace near the State Archive, Section 2, 2nd Floor, Tirana. The company was created to implement the concession contract for the construction of Dobjot i Madh, Arrëz, Miras, Menkulas, Bracen and Kuç hydropower plants.
Shareholders

Arela shpk - 25% of the shares
2T - 30% of the shares
Konstruksion 93 - 45% of the shares

Related Persons and Entities
Krenar Kadria - current administrator (07.08.2012 - 07.08.2017)
Valentina Tili - Administrator (17.08.2010 - 07.08.2012)

Location